Old Greenwich RR Station Upgrades and Bridge Replacement

Public Information Week of Feb. 17 thru Feb. 22

*NOTICES*

Construction Activities and Notices Regarding Pedestrian and Commuter Access:

  • Platforms on the bridge and West of the bridge are closed for bridge demolition. Pedestrian access will be limited to existing platforms East of the bridge.
  • Additional new platforms and shelter are also available at East end of the existing platform.
  • New stairs adjacent to new shelter at North Platform are now open for access to new platform sections. Please utilize.

Night Time Operations (2/17/19 to 2/21/19):

  • Track 3 outage and support work by Metro-North Railroad.
  • Excavate and install temporary platform support system at Sound Beach Avenue bridge.
  • Demo bridge deck at Sound Beach Avenue.

Daytime Operations (2/18/19 to 2/22/19):

  • Snow removal at sidewalks and bridge plates when needed.
  • Saw cutting bridge abutment walls at Sound Beach Avenue and Tomac Avenue.